In three years time, up to 7 Kurata Plants will be operating in Spain.

<!--:en-->Plant in Córdoba: Operative<!--:--><!--:es-->Planta en Córdoba: Operativa<!--:-->

Plant in Córdoba: Operative


  • Location: Cañete de las Torres, Córdoba
  • Opening: 2011
  • Number of Catalyst Units: 1
  • Raw Material: Used Industrial Oil
  • Final Product for Sale: approx. 8,890 Tn/year (Diesel)
<!--:en-->Plant in Cuenca: Under Construction<!--:--><!--:es-->Planta en Cuenca: En Desarrollo<!--:-->

Plant in Cuenca: Under Construction


  • Location: Barajas de Melo, Cuenca
  • Opening: 1st Half 2015
  • Number of Catalyst Units: 3
  • Raw Material: Used Industrial Oil
  • Final Product for Sale: approx. 26,680 Tn/year (Diesel)
<!--:en-->Plant in Almería: Under Construction<!--:--><!--:es-->Planta en Almería: En Desarrollo<!--:-->

Plant in Almería: Under Construction


  • Location: Almería
  • Opening: 2nd Half 2016
  • Number of Catalyst Units: 3
  • Raw Material: Plastics
  • Final Product for Sale: approx. 25,250 Tn/year (Diesel/LPG)
<!--:en-->Plant in Algeciras: Design Phase<!--:--><!--:es-->Planta en Algeciras: Fase Diseño<!--:-->

Plant in Algeciras: Design Phase


  • Location: Algeciras, Cádiz
  • Number of Catalyst Units: 3
  • Raw Material: Refinery Residue
  • Final Product for Sale: approx. 18,225 Tn/year (Diesel)
<!--:en-->Plant in Sevilla: Design Phase<!--:--><!--:es-->Planta en Sevilla: Fase Diseño<!--:-->

Plant in Sevilla: Design Phase


  • Location: Alcalá de Guadaira, Sevilla
  • Number of Catalyst Units: 3
  • Raw Material: Plastics
  • Final Product for Sale: approx. 25,250 Tn/year (Diesel/LPG)
<!--:en-->Plant in Granada: Design Phase<!--:--><!--:es-->Planta en Granada: Fase Diseño<!--:-->

Plant in Granada: Design Phase


  • Location: Granada
  • Number of Catalyst Units: 3
  • Raw Material: Plastics
  • Final Product for Sale: approx. 25,250 Tn/year (Diesel/LPG)
<!--:en-->Plant in La Coruña: Design Phase<!--:--><!--:es-->Kurata en La Coruña: Fase Diseño<!--:-->

Plant in La Coruña: Design Phase


  • Location: Cerceda, La Coruña
  • Number of Catalyst Units: 3
  • Raw Material: Plastics
  • Final Product for Sale: approx. 25,250 Tn/year (Diesel/LPG)